Dear Patrons,

Season’s greetings from SAS Infra!

With great pleasure, we share with you the construction update of SAS Crown, with the latest development captured on 3rd February 2024. We are glad to continue sharing these milestones with you as together, we shape the skyline of Hyderabad.

Should you require any further information, please feel free to reach us at +91 9718 66 22 99.


🏗️ Overall Construction Progress

Tower Building Current Progress
Tower 1 Building 1 Slab works for 40th floor in progress
Tower 1 Building 2 Slab works for 41st floor in progress
Tower 2 Building 3 Slab works for 42nd floor in progress
Tower 3 Building 4 Slab works for 52nd floor in progress
Tower 3 Building 5 Slab works for 53rd floor in progress

🏢 Interior Progress by Tower & Building

Tower 1 – Building 1

Activity Status
Water Proofing Completed till L-31, WIP in L-32 to L-36
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-31
Block Work Toilets till L-26, WIP in L-27,28; Flats WIP in L-17,18
Ceiling Electrical Works – Conduit Completed till L-30, WIP in L-31
PPR & CPVC Ceiling Lines Completed till L-21, WIP in L-22
Vertical Plumbing Shaft Line Completed L-5 to L-10, WIP L-11 to L-12
Gypsum Punning Completed till L-21, WIP in L-22 to L-24
Marble Laying Completed till L-6 (except Master & Powder toilets), WIP L-7 to L-9
Marble Polish Flats till L-6, Toilets till L-5, WIP in L-6
Internal Painting Completed till L-7, WIP in L-8 to L-14
Plumbing Shaft Painting Completed till L-14
Unitized Curtain Wall Completed till L-10
Internal Texture Completed till L-4, WIP in L-5 & 6

Tower 1 – Building 2

Activity Status
Waterproofing Completed till L-32, WIP in L-33 to L-36
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-31
Block Work Toilets till L-28, Flats WIP in L-22,23
Ceiling Electrical – Conduit Completed till L-31, WIP in L-32
PPR & CPVC Ceiling Lines Completed till L-26, WIP in L-27
Vertical Plumbing Shaft Line Completed L-4 to L-6, WIP L-7 to L-8
Gypsum Punning Completed till L-19
Marble Laying Completed till L-6 (except Master & Powder toilets), WIP L-7 to L-10
Internal Painting Completed till L-7, WIP in L-8 to L-14
Plumbing Shaft Painting Completed till L-14
Unitized Curtain Wall Completed till L-10
Internal Texture Completed till L-4, WIP in L-5 & 6

Tower 2 – Building 3

Activity Status
Water Proofing Completed till L-32, WIP in L-33,35 to L-37
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-31
Block Work Toilets till L-28, Flats WIP in L-22,23
Ceiling Electrical – Conduit Completed till L-31, WIP in L-32
PPR & CPVC Ceiling Lines Completed till L-26, WIP in L-27
Vertical Plumbing Shaft Line Completed L-4 to L-6, WIP L-7 to L-8
Gypsum Punning Completed till L-19
Marble Laying Completed till L-6 (except Master & Powder toilets), WIP L-7 to L-10
Marble Polish Flats till L-3, WIP in L-4
Internal Painting Completed till L-13, WIP in L-14 & 15
Plumbing Shaft Painting Completed till L-15
Unitized Curtain Wall Completed till L-10
Internal Texture WIP in L-3

Tower 3 – Building 4

Activity Status
Water Proofing Completed till L-40, WIP in L-41 to L-47
Plumbing – Soil Piping Completed till L-43
Sunken Filling Completed till L-40
Block Work Toilets till L-37, Flats WIP in L-22,23
Ceiling Electrical – Conduit Completed till L-37, WIP in L-38
PPR & CPVC Ceiling Lines Completed till L-30, WIP in L-33
Vertical Plumbing Shaft Line Completed L-4 to L-16, WIP L-17 to L-18
Gypsum Punning Completed till L-23, WIP in L-33
Marble Laying Completed till L-14 (except toilets), WIP L-15,16
Marble Polish Flats till L-13, WIP in L-14
Internal Toilets Completed till L-12, WIP in L-13
Tiles Flooring Completed till L-13, WIP in L-12
Internal Painting Completed till L-21, WIP in L-22
Plumbing Shaft Painting Completed till L-26
Unitized Curtain Wall Completed till L-10
Internal Texture Completed till L-23, WIP in L-24

Tower 3 – Building 5

Activity Status
Water Proofing Completed till L-40, WIP in L-41 to L-47
Plumbing – Soil Piping Completed till L-43
Sunken Filling Completed till L-40
Block Work Toilets till L-36, Flats WIP in L-22,23 & L-37
Ceiling Electrical – Conduit Completed till L-36 & 38, WIP in L-37,39
PPR & CPVC Ceiling Lines Completed till L-31, WIP in L-32
Vertical Plumbing Shaft Line Completed L-4 to L-16, WIP L-17 to L-18
Gypsum Punning Completed till L-23,26–28, WIP in L-32,37
Marble Laying Completed till L-12, WIP in L-13 to L-16
Marble Polish Flats till L-6,8,9,11,12; WIP in L-7,10,14
Internal Toilets WIP in L-7,9,11
Tiles Flooring Completed till L-13
Internal Painting Completed till L-17, WIP in L-18
Plumbing Shaft Painting Completed till L-28
Unitized Curtain Wall Completed till L-10
Internal Texture Completed till L-20,22,24,25; WIP in L-26,27

🎥 Video Update
Watch the construction update video here:
Construction Update Video


Best regards,
SAS Infra Team