I Tower Project Update 1.1 Nov 2023
I Tower Project Update 1.2 Nov 2023
I Tower Project Update 1.3 Nov 2023
I Tower Project Update 1.4 Nov 2023
I Tower Project Update 1.5 Nov 2023
I Tower Project Update Nov 2023

i-Tower Project Update – November 2023

Dear Patrons,

Season’s greetings from SAS Infra!

With great pleasure, we share you the construction update of SAS iTower, the latest development of which is shot on 4th November 2023. We are proud to announce that the main structure is complete. Currently, the Facade works and internal works are in progress. We are glad to continue sharing these milestones with you as together, we shape the skyline of Hyderabad. 

Should you require any further information please feel free to reach us at +91 9718 66 22 99.

 

Progress Update
  • Structure is completed
      • Tower A – 100% 
      • Tower C – 72%
  • Facade work is ongoing 
      • 85% – Completed
      • 15% – Ongoing
  • Internal works are in-progress
    • Fire Lift till Level 18 done (Pre-installation work is completed. Rest is in progress). 
  • Level 19 to 37 is under finishing stage

 

https://drive.google.com/file/d/1l1vsRjRV7q97V2J5cOzfXZnLPe_nHmiv/view?usp=sharing

 

Best regards, Team

Date: