Crown Project Update – October 2023

Dear Patrons,

 

Season’s greetings from SAS Infra!

With great pleasure, we share you the construction update of SAS Crown, the latest development of which is shot on 5th October 23. We are glad to continue sharing these milestones with you as together, we shape the skyline of Hyderabad. 

Should you require any further information please feel free to reach us at +91 9718 66 22 99.

Progress Update:

The project has made steady progress with each tower over the previous month. Here is the current progress of each tower: 

Tower 1 – Building 1: Slab works for 31st floor in progress

Tower 1 – Building 2: Slab works for 32nd floor in progress

Tower 2 – Building 3: Slab works for 33rd floor in progress

Tower 3 – Building 4: Slab works for 40th floor in progress

Tower 3 – Building 5: Slab works for 41st floor in progress

 

Interior Progress Update:

Here is the current progress of the interiors in Tower 1 – Building 1:

 

Tower 1 – Building 1: 
Water Proofing Completed till L-24, WIP in L-25,26
Plumbing – Soil Piping Completed till L-24
Sunken Filling Completed till L-24
Block Work Completed till L-20, WIP in L-21,22
Ceiling Electrical Works – Conduit Completed till L-20, WIP in L-21
PPR & CPVC Ceiling Lines Completed till L-17, WIP in L-18
Gypsum Punning till above 300mm from FFL Completed till L-7, WIP in L-8,9,10,11,12,13,14
Marble Laying WIP in L-3

 

Here is the current progress of the interiors in Tower 1 – Building 2:

 

Tower 1 – Building 2: 
Water Proofing Completed till L-25, WIP in L-26,27
Plumbing – Soil Piping Completed till L-25
Sunken Filling Completed till L-25
Block Work Completed till L-22, WIP in L-23
Ceiling Electrical Works – Conduit Completed till L-21, WIP in L-22
PPR & CPVC Ceiling Lines Completed till L-18, WIP in L-19
Gypsum Punning till above 300mm from FFL Completed till L-13, WIP in L-14,15

 

Here is the current progress of the interiors in Tower 2 – Building 3: 

 

Tower 2 – Building 3: 
Water Proofing Completed till L-26, WIP in L-27,28
Plumbing – Soil Piping Completed till L-26
Sunken Filling Completed till L-26
Block Work Completed till L-26
Ceiling Electrical Works – Conduit Completed till L-26
PPR & CPVC Ceiling Lines Completed till L-23, WIP in L-24,25
Gypsum Punning till above 300mm from FFL Completed till L-18, WIP in L-15,19,20
Marble Laying Completed till L-12, WIP in L-13 (Except in Master and Powder Toilet Pending)
Marble Polish Completed till L-6, WIP in L-7
Internal Painting Completed till L-5, WIP in L-6

 

Here is the current progress of the interiors in Tower 3 – Building 4: 

 

Tower 3 – Building 4: 
Water Proofing Completed till L-30, WIP in L-31,32,33,34
Plumbing – Soil Piping Completed till L-30
Sunken Filling Completed till L-30
Block Work Completed till L-27, WIP in L-28
Ceiling Electrical Works – Conduit Completed till L-26, WIP in L-27
PPR & CPVC Ceiling Lines Completed till L-22, WIP in L-23,24
Gypsum Punning till above 300mm from FFL Completed till L-18, WIP in L-19,20,21
Marble Laying Completed till L-10 (Except in Master and Powder Toilet Pending), WIP in L-12 
Marble Polish Completed till L-6
Internal Painting Completed till L-6, WIP in L-7,8,9
Texture Painting WIP in L-3

 

Here is the current progress of the interiors in Tower 3 – Building 5: 

 

Tower 3 – Building 5: 
Water Proofing Completed till L-30, WIP in L-31,32,33,34
Plumbing – Soil Piping Completed till L-30
Sunken Filling Completed till L-30
Block Work Completed till L-27
Ceiling Electrical Works – Conduit Completed till L-26, WIP in L-27
PPR & CPVC Ceiling Lines Completed till L-24, WIP in L-25
Gypsum Punning till above 300mm from FFL Completed till L-20, WIP in L-18,21
Marble Laying Completed till L-9 (Except in Master and Powder Toilet Pending), WIP in L-9,10
Marble Polish Completed till L-6, WIP in L-5
Internal Painting Completed till L-6, WIP in L-7,8,9
Texture Painting WIP in L-4, WIP in L-5

 

Best regards, Team