Crown Project Update Nov – 2023
Crown Project Update 1.3 Nov – 2023
Crown Project Update 1.2 Nov – 2023
Crown Project Update 1.1 Nov – 2023

Crown Project Update – November 2023

Dear Patrons,

 

Season’s greetings from SAS Infra!

With great pleasure, we share you the construction update of SAS Crown, the latest development of which is shot on 4th November 2023. We are glad to continue sharing these milestones with you as together, we shape the skyline of Hyderabad. 

Should you require any further information please feel free to reach us at +91 9718 66 22 99.

Progress Update:

The project has made steady progress with each tower over the previous month. Here is the current progress of each tower: 

Tower 1 – Building 1: Slab works for 33rd floor in progress

Tower 1 – Building 2: Slab works for 34th floor in progress

Tower 2 – Building 3: Slab works for 35th floor in progress

Tower 3 – Building 4: Slab works for 43rd floor in progress

Tower 3 – Building 5: Slab works for 44th floor in progress

 

Interior Progress Update:

Here is the current progress of the interiors in Tower 1 – Building 1:

 

Tower 1 – Building 1: 
Water Proofing Completed till L-26, WIP in L-27,28
Plumbing – Soil Piping Completed till L-26
Sunken Filling Completed till L-26
Block Work Completed till L-23, WIP in L-24
Ceiling Electrical Works – Conduit Completed till L-24, WIP in L-25
PPR & CPVC Ceiling Lines Completed till L-18, WIP in L-19
Gypsum Punning till above 300mm from FFL Completed till L-14, WIP in L-15
Marble Laying L-3 Flat Flooring Completed (Toilets WIP) & L-4 WIP

 

Here is the current progress of the interiors in Tower 1 – Building 2:

 

Tower 1 – Building 2: 
Water Proofing Completed till L-27, WIP in L-28
Plumbing – Soil Piping Completed till L-27
Sunken Filling Completed till L-27
Block Work Completed till L-24, WIP in L-25
Ceiling Electrical Works – Conduit Completed till L-24, WIP in L-25
PPR & CPVC Ceiling Lines Completed till L-19, WIP in L-20
Gypsum Punning till above 300mm from FFL Completed till L-15 WIP in L-16
Marble Laying L-3 (WIP)

 

Here is the current progress of the interiors in Tower 2 – Building 3: 

 

Tower 2 – Building 3: 
Water Proofing Completed till L-28, WIP in L-30,L-31
Plumbing – Soil Piping Completed till L-28
Sunken Filling Completed till L-28
Block Work Completed till L-26 , WIP in L-28
Ceiling Electrical Works – Conduit Completed till L-27, WIP in L-28
PPR & CPVC Ceiling Lines Completed till L-25, WIP in L-26
Gypsum Punning Completed till L-19, WIP in L-20
Marble Laying Completed till L-14 , WIP in L-15 (Except in Master and Powder toilet pending)
Marble Polish Completed till L-7, WIP in L-14
Tiles Flooring  Completed till L-13
Internal Painting Completed till L-5 , WIP in L-6
Plumbing Shaft Painting  Completed till L-14
UCW Completed till L-8 , WIP in L-9
Internal Texture Completed till L-4

Here is the current progress of the interiors in Tower 3 – Building 4: 

 

Tower 3 – Building 4: 
Water Proofing Completed till L-33, WIP in L-34,35,36,37,38
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-33
Block Work Completed till L-30, WIP in L-31
Ceiling Electrical Works – Conduit Completed till L-27, WIP in L-28
PPR & CPVC Ceiling Lines Completed till L-25, WIP in L-26
Gypsum Punning Completed till L-22, WIP in L-23
Marble Laying Completed till L-12 (Except in Master and Powder toilet pending)
Marble Polish Completed till L-6
Tiles Flooring Completed till L-9 ,WIP in L-6
Texture Painting WIP in L-3
Internal Painting Completed till L-10, WIP in L-11,12,13,14
Plumbing Shaft Painting Completed till L-14
Internal Texture Completed till L-11, WIP in L-12,13

 

Here is the current progress of the interiors in Tower 3 – Building 5: 

 

Tower 3 – Building 5: 
Water Proofing Completed till L-33, WIP in L-34,35,36,37,38
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-33
Block Work Completed till L-30 , WIP in L-31
Ceiling Electrical Works – Conduit Completed till L-28, WIP in L-30
PPR & CPVC Ceiling Lines Completed till L-25, WIP in L-26
Gypsum Punning Completed till L-22, WIP in L-23
Marble Laying Completed till L-10 (Except in Master and Powder toilet pending), WIP in L-11
Marble Polish Completed till L-5& L-6 , WIP in L-4
Tiles Flooring Completed till L-9 ,WIP in L-6
Internal Painting  Completed till L-8 , WIP in L-9,10
Plumbing Shaft Painting Completed till L-14
Texture Painting Completed till L-10, WIP in L-11,12

 

Best regards, Team