Crown Project Update 1.2 Jan – 2024
Crown Project Update 1.1 Jan – 2024
Crown Project Update Jan – 2024

Crown Project Update – January 2024

[vc_row][vc_column][vc_column_text]

Dear Patrons,

 

Season’s greetings from SAS Infra!

With great pleasure, we share you the construction update of SAS Crown, the latest development of which is shot on 2nd January 2024. We are glad to continue sharing these milestones with you as together, we shape the skyline of Hyderabad.

Should you require any further information please feel free to reach us at +91 9718 66 22 99.

Progress Update:

The project has made steady progress with each tower over the previous month. Here is the current progress of each tower: 

Tower 1 – Building 1: Slab works for 38th floor in progress

Tower 1 – Building 2: Slab works for 38th floor in progress

Tower 2 – Building 3: Slab works for 40th floor in progress

Tower 3 – Building 4: Slab works for 49th floor in progress

Tower 3 – Building 5: Slab works for 50th floor in progress

 

Interior Progress Update:

Here is the current progress of the interiors in Tower 1 – Building 1:

Tower 1 – Building 1: 
Water Proofing Completed till L-30 WIP in L-29,31,32,33,34
Plumbing – Soil Piping Completed till L-32
Sunken Filling Completed till L-30
Block Work Completed till L-26 WIP in L-27,28
Ceiling Electrical Works – Conduit Completed till L-30, WIP in L-31
PPR & CPVC Ceiling Lines Completed till L-21, WIP in L-22
Gypsum Punning till above 300mm from FFL Completed till L-19, WIP in L-20,21
Marble Laying Completed till L-5 (Except in Master and Powder toilet pending ) WIP in L-6,7,8
Marble Polish Internal Flats Completed till L-3 (Toilets WIP) & WIP in L-4
Internal Painting  Completed till L-3,4 WIP-L-7 to L-14
Unitize Curtain Wall Works Completed till L-7 WIP-L-7 to L-8

 

Here is the current progress of the interiors in Tower 1 – Building 2:

Tower 1 – Building 2: 
Water Proofing Completed till L-30 WIP in L-29,31,32,33,34,35
Plumbing – Soil Piping Completed till L-31
Sunken Filling Completed till L-30
Block Work Completed till L-28, WIP in L-30
Ceiling Electrical Works – Conduit Completed till L-28, WIP in L-30
PPR & CPVC Ceiling Lines Completed till L-24, WIP in L-25,26
Gypsum Punning Completed till L-16 WIP in L-17,18,19
Marble Laying  Completed till L-5 (Except in Master and Powder toilet pending) WIP in L- 6 & 7
Unitize Curtain Wall Works Completed till L-10

 

Here is the current progress of the interiors in Tower 2 – Building 3:

Tower 2 – Building 3: 
Water Proofing Completed till L-32 WIP in L-29,33,34,35,36,37
Plumbing – Soil Piping Completed till L-32
Sunken Filling Completed till L-31
Block Work Completed till L-31 , WIP in L-27
Ceiling Electrical Works – Conduit Completed till L-30, WIP in L-31
PPR & CPVC Ceiling Lines Completed till L-28, WIP in L-31
Vertical Pipe Line in Plumbing Shaft Completed till L-4 to L-12 WIP- L-13 to L-14
Gypsum punning Completed till L-22, WIP in L-23
Marble Laying Completed till L-16 (Toilets WIP) (Except in Master and Powder toilet pending) L-17 WIP
Marble Polish Internal Flats  Completed till L-14, L-8 Toilets WIP
Tiles Flooring  Completed till L-13 , WIP in L-14 & 15
Internal Painting Completed till L-10 , WIP in L-11,12,13,14,15
Plumbing Shaft Painting  Completed till L-14
UCW Completed till L-10
Internal Texture Completed till L-11 WIP in L-12 & 13

 

Here is the current progress of the interiors in Tower 3 – Building 4: 

Tower 3 – Building 4: 
Water Proofing Completed till L-39, WIP in L-40,41,42,43,44
Plumbing – Soil Piping Completed till L-40
Sunken Filling Completed till L-38
Block Work Completed till L-33, WIP in L-35,36
Ceiling Electrical Works – Conduit Completed till L-33, WIP in L-34
PPR & CPVC Ceiling Lines Completed till L-28, WIP in L-30
Vertical Pipe Line in Plumbing Shaft  Completed till L-4 to L-12 WIP- L-13 to L-14
Gypsum Punning Completed till L-23, WIP in L-24
Marble Laying Completed till L-13 (Except in Master and Powder toilet pending) WIP in L-14
Marble Polish Internal Flats Completed till L-12 , WIP in L-11 (Toilets)
Tiles Flooring Completed till L-9 
Internal Painting Completed till L-19, WIP in L-20
Plumbing Shaft Painting  Completed till L-26
UCW Completed till L-10
Internal Texture Completed till L-20, WIP in L-21

 

Here is the current progress of the interiors in Tower 3 – Building 5: 

Tower 3 – Building 5: 
Water Proofing Completed till L-39, WIP in L-40,41,42,43,44
Plumbing – Soil Piping Completed till L-40
Sunken Filling Completed till L-38
Block Work Completed till L-35 , WIP in L-36
Ceiling Electrical Works – Conduit Completed till L-32, WIP in L-33
PPR & CPVC Ceiling Lines Completed till L-28, WIP in L-30
Vertical Pipe Line in Plumbing Shaft  Completed till L-4 to L-12 WIP- L-13 to L-14
Gypsum Punning Completed till L-23, WIP in L-26,27,28
Marble Laying  Completed till L-11 (Except in Master and Powder toilet pending), WIP in L-12,13,14,15
Marble Polish  Completed till L-8 , WIP in L-7 & 9
Tiles Flooring Completed till L-9
Internal Painting  Completed till L-15, WIP in L-16,17,18
Plumbing Shaft Painting Completed till L-28
UCW Completed till L-10
Texture Painting Completed till L-18, WIP in L-19

 

Best regards, Team

[/vc_column_text][vc_video link=”https://drive.google.com/file/d/1wf-IdMa3FvbgvZePv5hbpcMkHJhW_HLu/view?usp=drive_link”][/vc_column][/vc_row]

Date: