Crown Project Update 1.1 Feb – 2024
Crown Project Update 1.2 Feb – 2024
Crown Project Update Feb – 2024

Crown Project Update – February 2024

Dear Patrons,

 

Season’s greetings from SAS Infra!

With great pleasure, we share you the construction update of SAS Crown, the latest development of which is shot on 3rd February 2024. We are glad to continue sharing these milestones with you as together, we shape the skyline of Hyderabad.

Should you require any further information please feel free to reach us at +91 9718 66 22 99.

Progress Update:

The project has made steady progress with each tower over the previous month. Here is the current progress of each tower: 

Tower 1 – Building 1: Slab works for 40th floor in progress

Tower 1 – Building 2: Slab works for 41th floor in progress

Tower 2 – Building 3: Slab works for 42nd floor in progress

Tower 3 – Building 4: Slab works for 52nd floor in progress

Tower 3 – Building 5: Slab works for 53rd floor in progress

 

Interior Progress Update:

Here is the current progress of the interiors in Tower 1 – Building 1:

Tower 1 – Building 1: 
Water Proofing Completed till L-31 WIP in L-32,33,34,35,36
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-31
Block Work Internal Toilets Completed till L-26 WIP in L-27,28 & Internal Flat WIP in L-17,18
Ceiling Electrical Works – Conduit Completed till L-30, WIP in L-31
PPR & CPVC Ceiling Lines Completed till L-21, WIP in L-22
Vertical Pipe Line in Plumbing Shaft Completed till L-5 to L-10 WIP- L-11 to L-12
Gypsum Punning  Completed till L-21, WIP in L-22,23,24
Marble Laying Completed till L-6 (Except in Master and Powder toilet pending ) WIP in L-7,8,9
Marble Polish Internal Flats Completed till L-6 & Internal Toilets Completed till L-5 WIP in L-6
Internal Painting Completed till L-7, WIP in L-8 to L-14
Plumbing Shaft Painting Completed till L-14
Unitize curtain wall works Completed till L-10
Internal Texture Completed till L-4 WIP in L-5 & 6

 

Here is the current progress of the interiors in Tower 1 – Building 2:

Tower 1 – Building 2: 
Waterproofing Completed till L-32 WIP in L-33,34,35,36
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-31
Block Work Internal Toilets Completed till L-28 Internal Flat WIP in L-22,23
Ceiling Electrical Works – Conduit Completed till L-31, WIP in L-32
PPR & CPVC Ceiling Lines Completed till L-26, WIP in L-27
Vertical Pipe Line in Plumbing Shaft Completed till L-4 to L-6 WIP- L-7 to L-8
Gypsum punning Completed till L-19
Marble Laying Completed till L-6 (Except in Master and Powder toilet pending ) WIP in L-7,8,9,10
Internal Painting Completed till L-7, WIP in L-8 to L-14
Plumbing Shaft Painting Completed till L-14
Unitize curtain wall works Completed till L-10
Internal Texture Completed till L-4 WIP in L-5 & 6

 

Here is the current progress of the interiors in Tower 2 – Building 3:

Tower 2 – Building 3: 
Water Proofing Completed till L-32 WIP in L-33,35,36,37
Plumbing – Soil Piping Completed till L-33
Sunken Filling Completed till L-31
Block Work Internal Toilets Completed till L-28 Internal Flat WIP in L-22,23
Ceiling Electrical Works – Conduit Completed till L-31, WIP in L-32
PPR & CPVC Ceiling Lines Completed till L-26, WIP in L-27
Vertical Pipe Line in Plumbing Shaft Completed till L-4 to L-6 WIP- L-7 to L-8
Gypsum punning Completed till L-19
Marble Laying Completed till L-6 (Except in Master and Powder toilet pending ) WIP in L-7,8,9,10
Marble Polish Internal Flats  Completed till L-3, WIP in L-4
Internal Painting Completed till L-13 , WIP in L-14 & 15
Plumbing Shaft Painting Completed till L-15
Unitize curtain wall works Completed till L-10
Internal Texture WIP in L-3

 

Here is the current progress of the interiors in Tower 3 – Building 4:

Tower 3 – Building 4: 
Water Proofing Completed till L-40, WIP in L-41,42,43,44,45,46,47
Plumbing – Soil Piping Completed till L-43
Sunken Filling Completed till L-40
Block Work Internal Toilets Completed till L-37, Internal Flat WIP in L-22,23
Ceiling Electrical Works – Conduit Completed till L-37, WIP in L-38
PPR & CPVC Ceiling Lines Completed till L-30, WIP in L-33
Vertical Pipe Line in Plumbing Shaft  Completed till L-4 to L-16 WIP- L-17 to L-18
Gypsum Punning Completed till L-23 WIP in L-33
Marble Laying Completed till L-14 (Except in Master and Powder toilet pending) WIP in L-15,16
Marble Polish Internal Flats Completed till L-13 WIP in L-14
Internal Toilets Completed till L-12 WIP in L-13
Tiles Flooring Completed till L-13, WIP in L-12
Internal Painting Completed till L-21, WIP in L-22
Plumbing Shaft Painting Completed till L-26
Unitize curtain Wall Works Completed till L-10
Internal Texture Completed till L-23, WIP in L-24

 

Here is the current progress of the interiors in Tower 3 – Building 5: 

Tower 3 – Building 5: 
Water Proofing Completed till L-40, WIP in L-41,42,43,44,45,46,47
Plumbing – Soil Piping Completed till L-43
Sunken Filling Completed till L-40
Block Work Internal Toilets Completed till L-36, Internal Flat WIP in L-37,22,23
Ceiling Electrical Works – Conduit Completed till L-36 & 38 WIP in L-37,39
PPR & CPVC Ceiling Lines Completed till L-31, WIP in L-32
Vertical Pipe Line in Plumbing Shaft  Completed till L-4 to L-16 WIP- L-17 to L-18
Gypsum Punning Completed till L-23,26,27,28 WIP in L-32,37
Marble Laying Completed till L-12 (Except in Master and Powder toilet pending), WIP in L-13,14,15,16
Marble Polish Internal Flat Completed till L-6,8,9,11,12 WIP in L-7,10,14
Internal Toilets WIP in L-7,9,11
Tiles Flooring Completed till L-13
Internal Painting Completed till L-17 , WIP in L-18
Plumbing Shaft Painting Completed till L-28
Unitize curtain Wall Works Completed till L-10
Internal Texture Completed till L-20,22,24,25 WIP in L-26,27

Best regards, Team

Date: