Progress Update:
The project has made steady progress with each tower over the previous month. Here is the current progress of each tower:
Tower 1 – Building 1: Slab works for 40th floor in progress
Tower 1 – Building 2: Slab works for 41th floor in progress
Tower 2 – Building 3: Slab works for 42nd floor in progress
Tower 3 – Building 4: Slab works for 52nd floor in progress
Tower 3 – Building 5: Slab works for 53rd floor in progress
Interior Progress Update:
Here is the current progress of the interiors in Tower 1 – Building 1:
Tower 1 – Building 1: | |
Water Proofing | Completed till L-31 WIP in L-32,33,34,35,36 |
Plumbing – Soil Piping | Completed till L-33 |
Sunken Filling | Completed till L-31 |
Block Work | Internal Toilets Completed till L-26 WIP in L-27,28 & Internal Flat WIP in L-17,18 |
Ceiling Electrical Works – Conduit | Completed till L-30, WIP in L-31 |
PPR & CPVC Ceiling Lines | Completed till L-21, WIP in L-22 |
Vertical Pipe Line in Plumbing Shaft | Completed till L-5 to L-10 WIP- L-11 to L-12 |
Gypsum Punning | Completed till L-21, WIP in L-22,23,24 |
Marble Laying | Completed till L-6 (Except in Master and Powder toilet pending ) WIP in L-7,8,9 |
Marble Polish Internal Flats | Completed till L-6 & Internal Toilets Completed till L-5 WIP in L-6 |
Internal Painting | Completed till L-7, WIP in L-8 to L-14 |
Plumbing Shaft Painting | Completed till L-14 |
Unitize curtain wall works | Completed till L-10 |
Internal Texture | Completed till L-4 WIP in L-5 & 6 |
Here is the current progress of the interiors in Tower 1 – Building 2:
Tower 1 – Building 2: | |
Waterproofing | Completed till L-32 WIP in L-33,34,35,36 |
Plumbing – Soil Piping | Completed till L-33 |
Sunken Filling | Completed till L-31 |
Block Work | Internal Toilets Completed till L-28 Internal Flat WIP in L-22,23 |
Ceiling Electrical Works – Conduit | Completed till L-31, WIP in L-32 |
PPR & CPVC Ceiling Lines | Completed till L-26, WIP in L-27 |
Vertical Pipe Line in Plumbing Shaft | Completed till L-4 to L-6 WIP- L-7 to L-8 |
Gypsum punning | Completed till L-19 |
Marble Laying | Completed till L-6 (Except in Master and Powder toilet pending ) WIP in L-7,8,9,10 |
Internal Painting | Completed till L-7, WIP in L-8 to L-14 |
Plumbing Shaft Painting | Completed till L-14 |
Unitize curtain wall works | Completed till L-10 |
Internal Texture | Completed till L-4 WIP in L-5 & 6 |
Here is the current progress of the interiors in Tower 2 – Building 3:
Tower 2 – Building 3: | |
Water Proofing | Completed till L-32 WIP in L-33,35,36,37 |
Plumbing – Soil Piping | Completed till L-33 |
Sunken Filling | Completed till L-31 |
Block Work | Internal Toilets Completed till L-28 Internal Flat WIP in L-22,23 |
Ceiling Electrical Works – Conduit | Completed till L-31, WIP in L-32 |
PPR & CPVC Ceiling Lines | Completed till L-26, WIP in L-27 |
Vertical Pipe Line in Plumbing Shaft | Completed till L-4 to L-6 WIP- L-7 to L-8 |
Gypsum punning | Completed till L-19 |
Marble Laying | Completed till L-6 (Except in Master and Powder toilet pending ) WIP in L-7,8,9,10 |
Marble Polish Internal Flats | Completed till L-3, WIP in L-4 |
Internal Painting | Completed till L-13 , WIP in L-14 & 15 |
Plumbing Shaft Painting | Completed till L-15 |
Unitize curtain wall works | Completed till L-10 |
Internal Texture | WIP in L-3 |
Here is the current progress of the interiors in Tower 3 – Building 4:
Tower 3 – Building 4: | |
Water Proofing | Completed till L-40, WIP in L-41,42,43,44,45,46,47 |
Plumbing – Soil Piping | Completed till L-43 |
Sunken Filling | Completed till L-40 |
Block Work | Internal Toilets Completed till L-37, Internal Flat WIP in L-22,23 |
Ceiling Electrical Works – Conduit | Completed till L-37, WIP in L-38 |
PPR & CPVC Ceiling Lines | Completed till L-30, WIP in L-33 |
Vertical Pipe Line in Plumbing Shaft | Completed till L-4 to L-16 WIP- L-17 to L-18 |
Gypsum Punning | Completed till L-23 WIP in L-33 |
Marble Laying | Completed till L-14 (Except in Master and Powder toilet pending) WIP in L-15,16 |
Marble Polish Internal Flats | Completed till L-13 WIP in L-14 |
Internal Toilets | Completed till L-12 WIP in L-13 |
Tiles Flooring | Completed till L-13, WIP in L-12 |
Internal Painting | Completed till L-21, WIP in L-22 |
Plumbing Shaft | Painting Completed till L-26 |
Unitize curtain Wall Works | Completed till L-10 |
Internal Texture | Completed till L-23, WIP in L-24 |
Here is the current progress of the interiors in Tower 3 – Building 5:
Tower 3 – Building 5: | |
Water Proofing | Completed till L-40, WIP in L-41,42,43,44,45,46,47 |
Plumbing – Soil Piping | Completed till L-43 |
Sunken Filling | Completed till L-40 |
Block Work | Internal Toilets Completed till L-36, Internal Flat WIP in L-37,22,23 |
Ceiling Electrical Works – Conduit | Completed till L-36 & 38 WIP in L-37,39 |
PPR & CPVC Ceiling Lines | Completed till L-31, WIP in L-32 |
Vertical Pipe Line in Plumbing Shaft | Completed till L-4 to L-16 WIP- L-17 to L-18 |
Gypsum Punning | Completed till L-23,26,27,28 WIP in L-32,37 |
Marble Laying | Completed till L-12 (Except in Master and Powder toilet pending), WIP in L-13,14,15,16 |
Marble Polish Internal Flat | Completed till L-6,8,9,11,12 WIP in L-7,10,14 |
Internal Toilets | WIP in L-7,9,11 |
Tiles Flooring | Completed till L-13 |
Internal Painting | Completed till L-17 , WIP in L-18 |
Plumbing Shaft | Painting Completed till L-28 |
Unitize curtain Wall Works | Completed till L-10 |
Internal Texture | Completed till L-20,22,24,25 WIP in L-26,27 |
Best regards,